EPCG pressures contractor to accelerate ecological reconstruction of Pljevlja Thermal Power Plant

Supported byOwner's Engineer banner

The management of EPCG has warned the contractor of delays, shortcomings, and irregularities in the ecological reconstruction of the Pljevlja Thermal Power Plant. The works, including the adaptation of the boiler and chimney, are being carried out by the consortium Dec International-Bemax-BB Solar-Permonte.

EPCG emphasized the need for urgent corrective measures so that the plant can be restarted by November 15, 2025. The contractor was instructed to provide precise recovery plans, address quality issues, and mobilize more skilled labor, subcontractors, and equipment, with work in shifts where necessary. EPCG gave the contractor a deadline of September 25 to eliminate irregularities and submit confirmation that all works will be completed on time.

Supported by

If sufficient progress is not made, EPCG will implement an alternative plan involving additional subcontractors. While this carries financial and quality risks, EPCG is negotiating with the contractor to formally approve subcontractor involvement. Discussions are ongoing regarding who will bear the costs.

Progress varies across projects. About 80 percent of work on the auxiliary boiler house has been completed, with Serbian subcontractor Tipo Kotlogradnja expected to accelerate pipeline connections. Pipeline works for slag and wastewater are significantly delayed, and an external firm may take over. Insulation of fuel oil and steam pipelines is partly agreed, with deadlines set for late September. The ash transport system is nearing completion, while cooling tower works are ongoing.

Supported byVirtu Energy

The ecological reconstruction aims to install desulfurization and denitrification systems, wastewater treatment, auxiliary fuel supply, a cooling tower, and noise protection. The project is expected to reduce negative impacts on air, water, and soil in line with EU and Montenegrin environmental legislation. It represents the most important investment to extend the plant’s operational life, ensure compliance with ecological standards, and improve efficiency, though challenges remain in meeting deadlines.